Automation payback calculator
Simple payback = upfront cost ÷ yearly savings. NPV discounts each year's savings back to today, and IRR is the discount rate that brings NPV to zero. In the worked example, a $185,000 robot cell saving a net $62,000 a year pays back in 2.98 years, has an NPV of $124,539 at a 10% discount rate over 7 years, and an IRR of 27.9%.
Check whether your project pays back
Enter what the project costs up front, what it saves each year after its own running costs, how long it lasts and your discount rate.
Equipment, integration, installation, training
Savings less the running costs it adds
Your cost of capital or hurdle rate
What it sells for at the end
- NPV
- $124,539.34
- IRR
- 27.9%
- Discounted payback
- 3.73 years
Show the working
- Simple payback: $185,000.00 ÷ $62,000.00 a year = 2.98 years, or 35.8 months.
- Present value of the savings: $62,000.00 × 4.8684 (7 years at 10%) = $301,841.97.
- Present value of the salvage: $15,000.00 ÷ 1.1^7 = $7,697.37.
- NPV: −$185,000.00 + $301,841.97 + $7,697.37 = $124,539.34.
- Discounted payback: 3.73 years, when the running total of discounted cash flows reaches zero.
- IRR: 27.95%, the discount rate at which NPV is zero. It is above the 10% discount rate, so the NPV is positive.
Show the cash flows year by year
| Year | Cash flow | Discounted | Running total | Discounted running total |
|---|---|---|---|---|
| 0 | -$185,000.00 | -$185,000.00 | -$185,000.00 | -$185,000.00 |
| 1 | $62,000.00 | $56,363.64 | -$123,000.00 | -$128,636.36 |
| 2 | $62,000.00 | $51,239.67 | -$61,000.00 | -$77,396.69 |
| 3 | $62,000.00 | $46,581.52 | $1,000.00 | -$30,815.18 |
| 4 | $62,000.00 | $42,346.83 | $63,000.00 | $11,531.66 |
| 5 | $62,000.00 | $38,497.12 | $125,000.00 | $50,028.78 |
| 6 | $62,000.00 | $34,997.38 | $187,000.00 | $85,026.16 |
| 7 | $77,000.00 | $39,513.18 | $264,000.00 | $124,539.34 |
The payback, NPV and IRR formulas
Yearly net savings are what the project saves (labor, scrap, overtime, energy) less what it adds to run (maintenance, power, software, spares). Savings are taken at the end of each year and assumed level. For savings that ramp up in the first year, enter a lower average or shorten the life.
Simple payback ignores the time value of money and everything after the payback date, so two projects with the same payback can be worth very different amounts. NPV covers both: it discounts each year's cash at the plant's discount rate (its cost of capital or hurdle rate) and adds them up. A positive NPV means the project earns more than that rate. IRR is the rate the project earns on its own cash flows; there is no formula for it, so the calculator finds it by bisection, halving the range of possible rates until NPV is zero.
When the cash flows never change sign, for example when the yearly savings are zero, no discount rate can bring NPV to zero. The calculator then says there is no IRR rather than printing a number.
Worked example
A plant prices a robot cell to palletize cases at the end of two packing lines. The robot, guarding, conveyor changes, integration and training come to $185,000. It frees one operator on each of two shifts from lifting, and after the cell's own maintenance and power the plant expects to save a net $62,000 a year. The finance team uses a 10% discount rate, the cell should last 7 years, and the robot should sell for about $15,000 at the end.
- Simple payback: $185,000.00 ÷ $62,000.00 a year = 2.98 years, or 35.8 months.
- Present value of the savings: $62,000.00 × 4.8684 (7 years at 10%) = $301,841.97.
- Present value of the salvage: $15,000.00 ÷ 1.1^7 = $7,697.37.
- NPV: −$185,000.00 + $301,841.97 + $7,697.37 = $124,539.34.
- Discounted payback: 3.73 years, when the running total of discounted cash flows reaches zero.
- IRR: 27.95%, the discount rate at which NPV is zero. It is above the 10% discount rate, so the NPV is positive.
What to count in the savings
Count savings that will show up in the plant's costs: operators moved to other work or overtime no longer paid, scrap no longer made, energy no longer used. Hours freed for people who stay on the same job are not a cash saving unless the time goes into output that sells. On the cost side, include integration, guarding, conveyor changes, training, spare parts, and the production lost while the equipment is installed.
Then test the decision, not just the number: rerun with savings 20% lower and a life two years shorter. A project that still clears the discount rate is robust; one that only works at the best case needs a closer look at its assumptions. The downtime cost and scrap cost calculators help put a figure on the losses a project would remove.
Payback here and on the ROI calculator
The ROI calculator answers a narrower question: whether AutoOps AI pays for itself in a plant, from reporting hours, scrap and downtime at three sets of assumptions. Its payback is also a simple, undiscounted payback, the yearly cost divided by the monthly savings, in months, because the cost there is a yearly subscription rather than a sum paid once. Use this page for equipment and automation, where a large amount is spent up front and the savings arrive over years.
Common mistakes
- Counting labor that doesn't leave. If the operator the robot frees still works the same shift on the same line, the payroll hasn't changed. Count a saving only where a cost actually goes away or output rises.
- Leaving out the running costs. Maintenance contracts, spare parts, power, software licences and a technician's time can take a large bite out of gross savings. Enter the net figure.
- Forgetting the ramp-up. New equipment rarely saves the full amount in its first months. In the example, a first year at half the savings moves simple payback out by about six months.
- Deciding on payback alone. A 2-year payback on a machine that lasts 3 years can be worth less than a 4-year payback on one that lasts 15. Check NPV over the whole life.
- Choosing the discount rate to get the answer. The discount rate should be the company's stated hurdle rate, set before the project is evaluated. Lowering it until the NPV turns positive defeats the purpose of the test.
Automation payback FAQ
How do you calculate payback for an automation project?
Simple payback = upfront cost ÷ yearly net savings. A $185,000 cell that saves a net $62,000 a year pays back in 2.98 years, about 36 months. Discounted payback does the same with each year's savings discounted to today's money, and comes out longer: 3.73 years at 10%.
What is NPV?
Net present value: the sum of all the project's cash flows, each discounted back to today at the plant's discount rate, including the upfront cost as a negative. A positive NPV means the project earns more than the discount rate over its life.
What is IRR and how is it found?
The internal rate of return is the discount rate at which NPV is exactly zero: the yearly return the project earns on its own cash flows. There is no formula for it, so it is found by search. This calculator narrows it down by bisection until the rate is exact to far more decimals than it shows.
What discount rate should I use?
Your company's cost of capital or hurdle rate, which finance usually sets. If you don't know it, ask before you run the numbers rather than picking a rate that flatters the project.
Why does it say there is no IRR?
Because the cash flows never change sign. With zero savings and no salvage, or no upfront cost, no discount rate makes NPV zero, so there is no rate to report.
What is a good payback period for automation?
Each company sets its own, and short paybacks are often asked of automation because products and technology change. NPV over the equipment's life is the better test of whether a project is worth doing; payback says how long the money is at risk.
Is anything I enter saved?
No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.