Downtime cost calculator

Downtime cost = hours down × (crew rate + machine rate), plus the margin on output that can't be made up. In the worked example, 135 minutes of unplanned stops on a sold-out machining cell cost $902.25: $317.25 of idle crew and machine time and $585.00 of lost margin.

Price your downtime

Enter the unplanned downtime for one machine or line over any period, and the hourly rates that apply to it.

min

Planned stops are not a loss

$ / h

Loaded cost of everyone idled

$ / h

Zero is allowed

units / h

Only to price lost output

$

Only if the output is lost for good

Downtime cost
$902.25
$6.68 a minute
Crew and machine
$317.25
Lost margin
$585.00
Lost output
90 units
Hours down
2.25 h
Show the working
  1. Hours down: 135 min ÷ 60 = 2.25 h.
  2. Crew and machine: 2.25 h × ($96.00 + $45.00) = $317.25.
  3. Lost output: 2.25 h × 40 units an hour = 90 units.
  4. Lost margin: 90 units × $6.50 = $585.00.
  5. Total: $317.25 + $585.00 = $902.25, or $6.68 a minute of downtime.

The downtime cost formula

Hours down = unplanned downtime minutes ÷ 60
Crew and machine cost = hours down × (crew labor rate + machine rate)
Lost output = hours down × planned units per hour
Lost margin = lost output × contribution margin per unit
Downtime cost = crew and machine cost + lost margin

The crew rate is the loaded cost of everyone who stands idle when the machine stops, per hour, not one person's wage. The machine rate is what the plant counts for an hour the machine should have been producing: depreciation or lease, energy at idle and similar costs. It can be zero.

Lost margin only belongs in the total when the output is truly lost: the machine is the constraint and the sale goes away. If the parts are made up later on overtime or a quiet shift, leave the margin at zero and price the overtime instead.

Worked example

A machining cell lost 135 minutes to unplanned stops in one week. Three operators stand idle when it stops, at a loaded $32 an hour each, so the crew rate is $96 an hour. The plant charges the machine at $45 an hour. The cell is planned at 40 parts an hour, it is the constraint on an order book that is sold out, and each part carries $6.50 of contribution margin.

  1. Hours down: 135 min ÷ 60 = 2.25 h.
  2. Crew and machine: 2.25 h × ($96.00 + $45.00) = $317.25.
  3. Lost output: 2.25 h × 40 units an hour = 90 units.
  4. Lost margin: 90 units × $6.50 = $585.00.
  5. Total: $317.25 + $585.00 = $902.25, or $6.68 a minute of downtime.

Common mistakes

  • Counting lost margin on output that is made up later. If the orders still ship, through overtime or a quiet shift, the margin isn't lost; the cost is the overtime. Count lost margin only when the stopped machine limits what the plant can sell.
  • Using revenue instead of contribution margin. A lost sale costs its price minus the variable costs you no longer spend (material, energy, piece-rate labor). Using the full price overstates the loss.
  • Pricing one operator instead of the crew. When a machine stops, everyone waiting on it is idle: the operator, the person loading it, the inspector downstream. The labor rate should cover all of them, loaded with benefits.
  • Including planned stops. Breaks, planned maintenance and scheduled changeovers are in the plan and the budget. Pricing them as downtime double-counts cost the plant already expected to carry.

Downtime cost FAQ

How do you work out the cost of downtime?

Multiply the hours lost by the hourly cost of what stood idle: the crew's loaded labor rate plus the machine's rate. If the lost output can't be made up and the sales are lost, add the lost units × the contribution margin per unit.

What should the machine rate include?

The costs per hour the plant carries whether the machine runs or not, such as depreciation or lease and energy at idle. A paid-off machine can have a machine rate of zero. Use the same rate the plant uses elsewhere so the figures agree.

Why use contribution margin rather than price?

Because when output is lost, the plant also doesn't spend the variable cost of making it. Contribution margin (price minus variable cost) is what the plant actually loses on each unit it can't sell.

What is the cost per minute useful for?

It turns minutes into money, so different stop reasons can be ranked by what they cost, and a spare part, a quicker changeover or more maintenance time can be weighed against the downtime it would save.

Is anything I enter saved?

No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.