OEE calculator
OEE = availability × performance × quality. It is the share of planned production time that turned into good parts at the ideal rate. In the worked example below, a shift with 440 planned minutes, 52 minutes of unplanned stops, a 30-second ideal cycle and 653 good parts out of 680 comes to 74.2%.
Work out OEE for one shift
Enter one shift, or any period with its planned stops, unplanned stops and part counts.
8 hours = 480
Breaks, meetings, planned maintenance
Breakdowns, jams, waiting
Fastest proven rate
Good and rejected
Right the first time
- Availability
- 88.2%
- Performance
- 87.6%
- Quality
- 96%
- Productive time
- 326.5 min
- Lost to stops
- 52 min
- Lost to slow cycles
- 48 min
- Lost to rejects
- 13.5 min
Show the working
- Planned production time: 480 − 40 min of planned stops = 440 min.
- Run time: 440 − 52 min of unplanned stops = 388 min.
- Availability: 388 ÷ 440 = 88.2%.
- Performance: 680 parts × 30 s = 20,400 s of ideal time, ÷ 23,280 s of run time = 87.6%.
- Quality: 653 good ÷ 680 made = 96%.
- OEE: 88.2% × 87.6% × 96% = 74.2%.
- Check: 653 good parts × 30 s = 19,590 s, ÷ 26,400 s of planned time = 74.2%.
The OEE formula
Each factor takes away one kind of loss. Availability loses the time the line was stopped. Performance loses speed: slow cycles and short stops nobody logged. Quality loses the time spent making parts that were scrapped or needed rework.
The last line is a useful check. Multiply out the three factors and most terms cancel, leaving the time it would have taken to make only the good parts at the ideal rate, as a share of planned time. Under the result, the four parts of planned time (stopped, slow, defective and productive) add back up to the planned minutes.
Worked example
A CNC cell runs one 480-minute shift with 40 minutes of planned stops (a 30-minute lunch and a 10-minute start-up meeting). It loses 52 minutes to unplanned stops: a tool break and two waits for material. The part's ideal cycle time is 30 seconds. The cell makes 680 housings, and 653 pass inspection the first time.
- Planned production time: 480 − 40 min of planned stops = 440 min.
- Run time: 440 − 52 min of unplanned stops = 388 min.
- Availability: 388 ÷ 440 = 88.2%.
- Performance: 680 parts × 30 s = 20,400 s of ideal time, ÷ 23,280 s of run time = 87.6%.
- Quality: 653 good ÷ 680 made = 96%.
- OEE: 88.2% × 87.6% × 96% = 74.2%.
- Check: 653 good parts × 30 s = 19,590 s, ÷ 26,400 s of planned time = 74.2%.
Common mistakes
- Using the average cycle time as the ideal. The ideal cycle time is the fastest the process is designed or proven to run, not what it usually does. Plug in today's average and performance sits near 100% while the slow cycles disappear from view.
- Moving losses into planned stops. Planned production time should only exclude time the line was never meant to run. Re-labelling changeovers or waits for material as planned makes availability look better while nothing changed on the floor. Decide once which stops are planned, write it down, and keep it.
- Counting reworked parts as good. Quality counts parts that were good the first time. A reworked part used the machine twice and the rework station once; counting it as good hides that loss.
- Averaging percentages across shifts or machines. Shifts and machines have different planned times, so a plain average of their percentages weights a short shift the same as a long one. Add up the minutes and counts first, then work out the three factors from the totals.
- Comparing figures across plants. OEE depends on which stops count as planned and which ideal cycle time is used, and plants choose differently. Compare a line with its own past, using the same definitions each time.
OEE FAQ
What is OEE?
OEE (overall equipment effectiveness) is the share of planned production time in which a machine or line makes good parts at its ideal rate. It multiplies three ratios: availability (the share of planned time it ran), performance (its speed while running, against the ideal) and quality (good parts out of all parts made).
What is the OEE formula?
OEE = availability × performance × quality. Availability = run time ÷ planned production time; performance = ideal cycle time × total count ÷ run time; quality = good count ÷ total count. The three multiply out to good count × ideal cycle time ÷ planned production time.
What is a good OEE?
There is no single right number, because the result depends on how planned stops and the ideal cycle time are defined. A figure of 85% is often quoted as world class for discrete manufacturing, but it is a rule of thumb. A line's own history, measured the same way each time, is the better comparison.
Why is my performance over 100%?
Because the line ran faster than the ideal cycle time you entered, which means the ideal is too slow. Use the fastest rate the process is designed or proven to run, such as the nameplate rate or the best sustained rate you have recorded.
Should changeovers count as planned stops or downtime?
Counting changeovers as unplanned stops keeps them in availability, so shorter changeovers show up in the result. Counting them as planned stops hides them. Either can be defended, as long as the same rule is used for every line and every period.
What is the difference between OEE and TEEP?
OEE measures against planned production time. TEEP (total effective equipment performance) measures against all calendar time, so it also counts the hours the line was not scheduled. TEEP = OEE × planned production time ÷ calendar time.
Is anything I enter saved?
No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.