Free tool · No login

Machine requirement calculator

Machines required = (demand × cycle time + set-up time) ÷ (available time per machine × efficiency), rounded up. In the worked example, 4,800 shafts a week at 150 seconds each, plus 4.5 hours of set-ups, need 3.41 lathes at 75 available hours and 80% efficiency: 4 lathes, loaded to 85%.

Work out how many machines you need

Enter one period, such as a week: the demand, the cycle time on one machine, each machine's available hours and the efficiency you plan at.

units

Good units needed

s / unit

On one machine

h

Same period, after planned stops

%

Share of time that makes good output

set-ups
min
Machines required
4
3.41 before rounding up
Loading
85.2%
Load
204.5 h
Effective time per machine
60 h
Spare on the rounded count
35.5 h
Show the working
  1. Run time: 4,800 units × 150 s = 720,000 s, or 200 h.
  2. Set-ups: 6 × 45 min = 270 min, or 4.5 h. Load: 204.5 h.
  3. Effective time per machine: 75 h × 80% = 60 h.
  4. Machines: 204.5 h ÷ 60 h = 3.408, rounded up to 4.
  5. Loading on 4 machines: 3.408 ÷ 4 = 85.2% of their effective time, leaving 35.5 h spare in the period.

The machine requirement formula

Load = demand × cycle time + number of set-ups × time per set-up
Effective time per machine = available time × efficiency
Machines required = load ÷ effective time per machine, rounded up
Loading = load ÷ (machines × effective time per machine)

Use one period for everything: a week's demand, a week's set-ups, and the hours each machine is available in that week after planned stops such as breaks and planned maintenance. The cycle time is per unit on one machine. For a machine that makes several parts in one cycle, divide its cycle time by the number of parts.

Efficiency is the share of available time that turns into good output at the cycle time you entered. An OEE figure from the machine's own history fits this slot when you enter the ideal cycle time, because it already counts stops, slow cycles and rejects. If you would rather add expected rejects to the demand, use availability × performance instead, so quality losses aren't counted twice. Enter 100% to size on the cycle time alone, which gives the theoretical minimum.

Loading is the unrounded machine count divided by the rounded one: the share of the rounded count's effective time that the plan uses. Rounding up always leaves some spare. A loading close to 100% leaves no room for a bad week.

Worked example

A turning department has to make 4,800 shafts a week. Each shaft takes 150 seconds on a CNC lathe. The lathes run two 7.5-hour shifts, five days a week, so each one is available 75 hours. Past weeks show about 80% of that time turns into good shafts at the 150-second cycle, after stops, slow cycles and rejects. The weekly mix needs 6 set-ups of 45 minutes each across the department.

  1. Run time: 4,800 units × 150 s = 720,000 s, or 200 h.
  2. Set-ups: 6 × 45 min = 270 min, or 4.5 h. Load: 204.5 h.
  3. Effective time per machine: 75 h × 80% = 60 h.
  4. Machines: 204.5 h ÷ 60 h = 3.408, rounded up to 4.
  5. Loading on 4 machines: 3.408 ÷ 4 = 85.2% of their effective time, leaving 35.5 h spare in the period.

When several parts share the machines

Work out the load for each part (its demand × its cycle time, plus its own set-ups), add the loads together, and divide the total by the effective time of one machine. Sizing each part on its own and adding the rounded counts overstates the need, because the part-machines each product leaves over can be shared: two parts that need 1.3 machines each need 2.6 together, so 3 machines, not 4.

Then look at the loading. A department planned at 85% keeps about 15% of its effective time spare for breakdowns, quality holds and demand spikes. One planned at 98% will fall behind the first time anything goes wrong, and the usual fixes are fewer set-ups, a proven higher efficiency, or another machine.

Machine counts in Capacity Line

Capacity Line, a tool in the AutoOps AI app, does this sum for each product's operations from an uploaded workbook: the operation's load (demand × cycle time, plus a set-up for each batch) against one resource's available time after its availability factor and the calendar's performance factor, rounded up and shown as required against available resources, with the utilization of the resources you have. Its takt and station balancing run on the same code as the free takt time and line balancing calculators.

Common mistakes

  • Sizing on the ideal cycle at 100% efficiency. Machines lose time to stops, slow cycles and rejects. Sizing on the ideal cycle time at 100% gives the theoretical minimum, which a real department rarely reaches. Use an efficiency you have measured on these machines.
  • Counting changeovers twice. If your efficiency figure already treats changeovers as lost time, leave the set-up fields at zero, or the same hours come off twice and the count comes out high.
  • Mixing periods. A week's demand against a day's available hours is out by a factor of five or more. Put the same period on both sides of the division.
  • Rounding each part before adding. Rounding each product's machine count up and then adding the rounded numbers buys capacity for the leftover fractions several times over. Add the loads first, then round once.
  • Planning shared machines to 100%. A loading in the high nineties leaves nothing for a breakdown, a quality hold or an urgent order. Keep planned loading on shared machines below that, and use the spare hours for maintenance and set-up reduction.

Machine requirement FAQ

How do you calculate the number of machines required?

Divide the machine time the demand needs (demand × cycle time, plus set-up time) by the effective time one machine offers in the same period (available hours × efficiency), and round up. In the worked example, 204.5 hours ÷ 60 hours = 3.41, so 4 machines.

Should I use OEE or efficiency in the formula?

Either, as long as it matches the cycle time. With the ideal cycle time, an OEE-type figure from the machine's history covers stops, slow cycles and rejects. With an average cycle time that already includes slow cycles, use availability alone and add expected rejects to the demand.

Why round up?

Because a fraction of a machine can't be bought or staffed. 3.41 machines means the fourth one is needed; the loading shows how much of the four machines' time the plan uses.

What is a good machine loading?

There is no single target. Bottleneck machines are often planned with enough spare to recover a bad week, while machines that are not the bottleneck can run lower without costing output. A plan above about 95% has very little room for problems.

How do I include set-ups?

Enter the number of set-ups in the period and the minutes each takes; the calculator adds them to the load. More, smaller batches mean more set-ups, which can push the machine count up; shorter set-ups bring it back down.

Is anything I enter saved?

No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.

See your own lines against their normal range.

On a plant account, upload a production export (.xlsx or .csv) and map its columns once. Plant today then compares each line's output, scrap and downtime with that line's own normal range, and every figure links to its source rows.