Free tool · No login

Yamazumi chart maker

A Yamazumi chart stacks each station's work content as a bar, split into value-added work, necessary non-value-added work and waste, with takt time drawn across it. Bars above the line can't keep pace, and the waste segments show what to remove before any work moves between stations. Paste one station per line to draw yours.

Make your Yamazumi chart

One station per line: its name, then value-added, necessary non-value-added and waste seconds, separated by commas or tabs, as in "Fasten, 35, 12, 9".

s

From the takt time calculator

Paste four columns from a spreadsheet, up to 30 stations. A header row is skipped.

Work content260 s
Value-added share55.4%
Minimum stations5
Balance efficiency86.7%
Bottleneck68 s
Stations without waste4

One station is over the 60 s takt: Wire harness (68 s). Remove the waste there first, then move work if it is still over. Waste is 41 s of the 260 s of work.

  • Value-added
  • Necessary non-value-added
  • Waste
  • Takt time
0 s20 s40 s60 sLoad and clamp: 48 s (value-added 28 s, non-value-added 14 s, waste 6 s)Load and clampFasten: 56 s (value-added 35 s, non-value-added 12 s, waste 9 s)FastenWire harness: 68 s (value-added 41 s, non-value-added 15 s, waste 12 s), 8 s over takt68 sWire harnessTest: 44 s (value-added 22 s, non-value-added 18 s, waste 4 s)TestPack: 44 s (value-added 18 s, non-value-added 16 s, waste 10 s)PackTakt 60 s
Work content by station
StationValue-addedNon-value-addedWasteTotalvs takt
Load and clamp28 s14 s6 s48 s12 s idle
Fasten35 s12 s9 s56 s4 s idle
Wire harness41 s15 s12 s68 s8 s over
Test22 s18 s4 s44 s16 s idle
Pack18 s16 s10 s44 s16 s idle
Show the working
  1. Station times: Load and clamp 28 + 14 + 6 = 48 s; Fasten 35 + 12 + 9 = 56 s; Wire harness 41 + 15 + 12 = 68 s; Test 22 + 18 + 4 = 44 s; Pack 18 + 16 + 10 = 44 s.
  2. Work content: 144 s value-added + 75 s non-value-added + 41 s waste = 260 s. Value-added share: 55.4%.
  3. Minimum stations: 260 ÷ 60 = 4.33, rounded up to 5. The line has 5.
  4. Balance efficiency: 260 ÷ (5 × 60) = 86.7%.
  5. Over takt: Wire harness by 8 s. The line can't keep takt until that work moves or the waste in it is removed.
  6. Without the waste: 219 ÷ 60 = 3.65, so 4 stations could carry the work if it were rebalanced.

How the chart is built

Station time = value-added + necessary non-value-added + waste
Work content = sum of all station times
Minimum stations = work content ÷ takt, rounded up
Balance efficiency = work content ÷ (stations × takt)
Stations without waste = (value-added + non-value-added) ÷ takt, rounded up

Yamazumi is Japanese for "stacked up". Each bar is one station or one operator, built from the elements of its work, and the dashed line is takt time. A bar above takt is a station that can't keep up with demand; a bar well below takt has idle time.

Value-added work changes the product in a way the customer pays for: fastening, wiring, machining. Necessary non-value-added work doesn't, but can't be dropped with today's method: picking parts, scanning a label, loading a fixture. Waste can be dropped: walking, searching, waiting, rework.

The chart suggests an order of work. Remove waste first, shrink the necessary non-value-added work second, then rebalance what is left so every station sits just under takt. Rebalancing first only moves the waste from one station to another.

Worked example

A five-station line assembles a small control cabinet to a 60-second takt. A team filmed ten cycles at each station and split every station's average time into value-added work (fastening, wiring, testing), necessary non-value-added work (picking parts, scanning, loading the fixture) and waste (walking to a rack, searching for a tool, waiting for the tester).

  1. Station times: Load and clamp 28 + 14 + 6 = 48 s; Fasten 35 + 12 + 9 = 56 s; Wire harness 41 + 15 + 12 = 68 s; Test 22 + 18 + 4 = 44 s; Pack 18 + 16 + 10 = 44 s.
  2. Work content: 144 s value-added + 75 s non-value-added + 41 s waste = 260 s. Value-added share: 55.4%.
  3. Minimum stations: 260 ÷ 60 = 4.33, rounded up to 5. The line has 5.
  4. Balance efficiency: 260 ÷ (5 × 60) = 86.7%.
  5. Over takt: Wire harness by 8 s. The line can't keep takt until that work moves or the waste in it is removed.
  6. Without the waste: 219 ÷ 60 = 3.65, so 4 stations could carry the work if it were rebalanced.

From the chart to a new balance

In the example, the wire harness station is 8 seconds over takt and carries 12 seconds of waste. Removing that waste alone brings it to 56 seconds, under takt, without moving any work. Across the line, removing all 41 seconds of waste leaves 219 seconds of work, which four stations could carry at a 60-second takt, so one operator could move to other work once the line is rebalanced.

To rebalance with task precedence, enter the remaining task times and their must-follow links in the line balancing calculator. If you don't have takt yet, work it out with the takt time calculator.

Common mistakes

  • Charting averages that hide variation. A station averaging 55 seconds against a 60-second takt may take 70 on a bad cycle. For stations close to takt, note the range of cycle times as well as the average.
  • Mixing up necessary work and waste. If the customer requires a scan, scanning is necessary non-value-added work. If walking to a rack is only needed because the rack is in the wrong place, it is waste. Agree the categories before you film.
  • Rebalancing before removing waste. Moving tasks around first spreads the waste across stations, where it is harder to see and harder to remove.
  • Building the chart from the routing. Walking, waiting for the tester and fetching labels are rarely on a routing sheet, but they take station time. Time or film the stations as they run.
  • One bar for several operators. A station with two operators has twice the time available in each takt. Draw one bar per operator, or divide the station's work by the number of people working it.

Yamazumi chart FAQ

What is a Yamazumi chart?

A stacked bar chart of the work at each station or operator, split into value-added work, necessary non-value-added work and waste, with takt time drawn as a line. It shows which stations are over takt, where the idle time is, and how much of the work is waste.

How do you make a Yamazumi chart?

Time or film several cycles at each station, break each cycle into elements, average them, and put each element into value-added, necessary non-value-added or waste. Stack the three for each station and draw a line at takt time.

What is the difference between a Yamazumi chart and line balancing?

A Yamazumi chart shows the work as it is today and how much of it is waste. Line balancing assigns tasks to stations to fit takt. Use the chart to find and remove the waste, then balance what is left.

What is value-added work?

Work that changes the form, fit or function of the product in a way the customer is willing to pay for, such as fastening, welding, machining or assembling. Inspecting, moving and waiting are not value-added, even when they are necessary.

What does "stations without waste" mean?

The fewest stations the remaining work would need at your takt if all the waste were removed: (value-added + non-value-added) ÷ takt, rounded up. It is a target for rebalancing, not a promise, because task sizes and precedence can force more stations.

Can I paste data from a spreadsheet?

Yes. Copy four columns: station name, value-added seconds, non-value-added seconds and waste seconds. A header row is skipped. Use 0 where a station has none of a category.

Is anything I enter saved?

No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.

See your own lines against their normal range.

On a plant account, upload a production export (.xlsx or .csv) and map its columns once. Plant today then compares each line's output, scrap and downtime with that line's own normal range, and every figure links to its source rows.