Standard time calculator
Standard time = observed time × performance rating × (1 + allowances). It is the time a trained operator needs for one unit at a normal pace, plus time for personal needs, fatigue and unavoidable delays. In the worked example, twelve cycles averaging 36 seconds, rated at 110% with 12% allowances, give a standard time of 44.4 seconds.
Turn your time study into a standard
Paste the cycle times from one study, in seconds, in the order you timed them. Then rate the operator's pace and enter your plant's allowances.
Separated by new lines, commas, tabs or spaces. Leave out abnormal cycles (a dropped part, a jam).
100 = normal pace
Unavoidable delays only
- Observed time
- 36 s
- Normal time
- 39.6 s
- Allowances
- 12%
- On working time instead
- 45 s
- Standard output
- 81.2 units / hour
- Cycles needed (±5%, 95%)
- 11 (you timed 12)
Show the working
- Observed time: 432 s ÷ 12 cycles = 36 s (sample standard deviation 2.931 s).
- Normal time: 36 s × 110% rating = 39.6 s.
- Allowances: 5% personal + 4% fatigue + 3% delay = 12%.
- Standard time on normal time: 39.6 × (1 + 0.12) = 44.352 s.
- On the other convention it would be 45 s, 0.648 s longer.
- Standard output: 3,600 s ÷ 44.352 s = 81.2 units an hour.
- Cycles needed for ±5% at 95% confidence: (1.96 × 2.931 ÷ (0.05 × 36))² = 10.18, rounded up to 11. The 12 timed cycles are enough.
The standard time formula
The performance rating adjusts for how fast the operator you timed was working. 100% is the pace of a trained operator working steadily without hurrying. 110% means the timed operator was 10% faster than that, so the normal time comes out longer than the time you saw. Rating takes judgement and practice, which is why studies are best done by someone trained in it and checked against a second rater now and then.
There are two ways to apply allowances, and both are in use. On normal time, an allowance of 12% adds 12% of the job's own time. On working time, 12% of the working day is set aside for allowances, so the work fills the other 88% and the standard is normal time ÷ 0.88. For the same percentage the second gives a longer standard: 45.0 seconds instead of 44.4 in the example, and the gap grows with the allowance. Use whichever convention your plant's policy states, and say which one when you quote a standard. The calculator shows both.
The last line checks whether you timed enough cycles. It takes the spread of your own cycles (their sample standard deviation, s) and works out how many cycles it takes to know the average within ±5% at 95% confidence. When the answer is more than you timed, keep timing.
Worked example
An engineer times an operator fitting and torquing a hinge bracket on a door subassembly: twelve cycles, read from a stopwatch in seconds. The operator worked steadily and somewhat faster than a normal pace, so the engineer rates the study at 110%. The plant's allowance policy is 5% personal, 4% fatigue and 3% unavoidable delay, added on normal time.
- Observed time: 432 s ÷ 12 cycles = 36 s (sample standard deviation 2.931 s).
- Normal time: 36 s × 110% rating = 39.6 s.
- Allowances: 5% personal + 4% fatigue + 3% delay = 12%.
- Standard time on normal time: 39.6 × (1 + 0.12) = 44.352 s.
- On the other convention it would be 45 s, 0.648 s longer.
- Standard output: 3,600 s ÷ 44.352 s = 81.2 units an hour.
- Cycles needed for ±5% at 95% confidence: (1.96 × 2.931 ÷ (0.05 × 36))² = 10.18, rounded up to 11. The 12 timed cycles are enough.
Putting the standard to work
A standard time feeds most of the planning that follows it. Standard output per hour is 3,600 ÷ the standard time in seconds: 81 hinge brackets an hour in the example. Compare each station's standard with takt from the takt time calculator, and spread the tasks across stations with the line balancing calculator.
Review a standard when the method, the equipment, the material or the product changes, not only when output disagrees with it. For a long or varied job, time each element (pick, place, fasten, inspect) separately, find the standard for each, and add them up: element times show where the time goes and make the study easier to repeat.
Common mistakes
- Timing too few cycles. Three or four cycles can't separate the job's real time from one fast or slow cycle. Time at least ten, read the cycles-needed line, and keep timing if it asks for more.
- Leaving abnormal cycles in, or taking normal ones out. A cycle in which the operator dropped a part or the fixture jammed doesn't belong in the average: note it and leave it out. A cycle that is simply slow is part of the job, and removing every slow cycle gives a standard nobody can meet.
- Rating everyone at 100%. Skipping the rating sets the standard at whatever pace the timed operator happened to work. A fast operator gives a standard others miss; a slow one gives a loose standard. Rate every study, even when the answer is 100%.
- Mixing allowance conventions. A 15% allowance on normal time and a 15% allowance on working time give standards about 2% apart. Applying a policy written for one convention with the formula of the other quietly shifts every standard.
- Hiding fixable delays in the allowance. Waiting for material, looking for tools and walking to a distant rack often end up in the delay allowance because they happen every day. They are losses to remove. Keep the delay allowance for interruptions that can't reasonably be avoided.
Standard time FAQ
What is standard time?
The time a trained operator needs to complete one unit of a job at a normal pace, using the agreed method, plus allowances for personal needs, fatigue and unavoidable delays. It is the basis for capacity plans, labor costing, line balancing and incentive schemes.
How do you calculate standard time?
Average the timed cycles to get the observed time, multiply by the performance rating to get normal time, then add allowances: standard time = normal time × (1 + allowance), or normal time ÷ (1 − allowance) if your allowances are set as a share of the working day.
What is the difference between normal time and standard time?
Normal time is the time for the work alone at a normal pace: the observed time adjusted by the performance rating. Standard time adds the allowances. A job with a normal time of 39.6 seconds and 12% allowances on normal time has a standard time of 44.4 seconds.
What are PF&D allowances?
Personal, fatigue and delay allowances. Personal covers drinks and restroom breaks; fatigue covers the recovery that a job's effort, posture and conditions call for; delay covers short, unavoidable interruptions that are part of the job. Your plant's policy or a published allowance table sets the percentages.
What performance rating should I use?
The one that reflects how the timed operator's pace compared with a normal pace. Raters train on films of known pace. Most ratings fall between 80% and 120%; a rating far outside that range suggests the study timed someone still learning the job or working in an unusual way.
How many cycles should I time?
Enough that the average is stable. A common check is n = (z × s ÷ (k × x̄))², where s is the standard deviation of your cycles, x̄ their average, k the accuracy you want (0.05 for ±5%) and z the normal value for your confidence level (1.96 for 95%). The calculator runs this check for ±5% at 95%.
Is this the same as a predetermined motion time system?
No. A predetermined motion time system builds a time from tables of basic motions without a stopwatch, often before the job exists. This calculator takes stopwatch times from the job as it runs today. Both end in a normal time to which allowances are added.
Is anything I enter saved?
No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.