Learning curve calculator
Wright's learning curve: every time cumulative output doubles, the average time per unit so far falls to a fixed percentage of what it was. That percentage is the learning rate. At 85%, a job whose first unit took 120 minutes averages 102 minutes over the first two units and 53.2 minutes over the first 32, by which point a single unit takes about 40.9 minutes.
Project your learning curve
Enter the first unit's time, the learning rate and the unit you want to know about. Add a target to see when the ramp-up reaches it.
Minutes or hours: answers use the same unit
85 = 15% faster per doubling
The unit to report on
A takt or standard to reach
- Cumulative average
- 53.24
- Total for 32 units
- 1,703.83
- Exponent b
- -0.2345
- Reaches the target at
- unit 22
Show the working
- Exponent: b = log(0.85) ÷ log 2 = -0.2345.
- Cumulative average at unit 32: 120 × 32^-0.2345 = 53.24.
- Total for 32 units: 53.24 × 32 = 1,703.83.
- Time of unit 32 alone: total for 32 − total for 31 = 1,703.83 − 1,662.92 = 40.91.
- Each doubling of output cuts the cumulative average to 85% of what it was: unit 1 averages 120, unit 2 averages 102, unit 4 averages 86.7, unit 8 averages 73.7, unit 16 averages 62.64, unit 32 averages 53.24.
- Target 45: unit 22 is the first to take 45 or less (44.75).
| Unit | Cumulative average | Total so far | This unit |
|---|---|---|---|
| 1 | 120 | 120 | 120 |
| 2 | 102 | 204 | 84 |
| 4 | 86.7 | 346.8 | 68.55 |
| 8 | 73.7 | 589.56 | 57.29 |
| 16 | 62.64 | 1,002.25 | 48.31 |
| 32 | 53.24 | 1,703.83 | 40.91 |
The learning curve formulas
This is Wright's cumulative-average model, first published for aircraft production in the 1930s and still the most common form. The learning rate applies to the cumulative average: at 85%, the average over the first 2 units is 85% of unit 1, the average over the first 4 is 85% of that, and so on.
Crawford's unit model, common in defense and aerospace cost estimating, applies the same power law to each unit's own time instead: unit 2 takes 85% of unit 1, unit 4 takes 85% of unit 2. With the same rate and first unit, Crawford's model predicts longer unit times and a larger total than Wright's. A rate measured under one model doesn't carry over to the other, so check which model your rate came from.
Times can be in any unit, minutes or hours; the answers come back in the same unit. The optional target finds the first unit whose own time is at or below a takt time or a quoted standard.
Worked example
A plant starts building a new pump skid. The first skid took a crew 120 minutes of assembly. Records from an earlier, similar product suggest an 85% learning rate. The first order is for 32 skids, and the line is balanced for a 45-minute takt.
- Exponent: b = log(0.85) ÷ log 2 = -0.2345.
- Cumulative average at unit 32: 120 × 32^-0.2345 = 53.24.
- Total for 32 units: 53.24 × 32 = 1,703.83.
- Time of unit 32 alone: total for 32 − total for 31 = 1,703.83 − 1,662.92 = 40.91.
- Each doubling of output cuts the cumulative average to 85% of what it was: unit 1 averages 120, unit 2 averages 102, unit 4 averages 86.7, unit 8 averages 73.7, unit 16 averages 62.64, unit 32 averages 53.24.
- Target 45: unit 22 is the first to take 45 or less (44.75).
Planning a ramp-up with the curve
Plan today's capacity from the unit time and the cost of a whole order from the total. In the example, the 32nd skid takes about 41 minutes, but the order as a whole averages 53. A plan that charges 41 minutes to every skid in the order comes up short by about 395 crew-minutes.
The target answers the usual ramp-up question directly: which unit is the first to come in at or under the takt or standard you have to hit. In the example it is unit 22, so the first 21 skids need extra time, overtime or another pair of hands. Rates for a new job are best taken from the plant's own history with similar work. For manual assembly, rates between 75% and 90% are often quoted; work paced by a machine learns less, with rates closer to 100%, because the machine sets most of the time.
A curve describes one job with the same method and crew in steady production. A long break, a crew change or a design change moves you back up the curve; resume from an earlier unit number rather than from where production stopped.
Common mistakes
- Using the cumulative average as today's unit time. The cumulative average still carries every slow early unit. The latest unit is quicker. Plan current capacity from the unit time and the cost of the whole order from the total.
- Mixing Wright's and Crawford's models. A learning rate fitted under one model gives the wrong answers in the other. Record which model a rate comes from when you save it.
- Starting the curve at a prototype. Prototype and pilot builds often use different tooling, people and methods. Start the curve at the first unit built on the real line by the real crew.
- Expecting learning to go on forever. Real curves flatten once the method stops changing or a machine sets the pace. Past that point, further gains come from changing the method, not from repetition.
- Ignoring breaks in production. After weeks away from a job, people forget part of what they learned. Restart from an earlier unit when production resumes.
Learning curve FAQ
What is a learning curve in manufacturing?
A model of how the time or cost to make a unit falls as a crew makes more of them. Wright's version says that every time cumulative output doubles, the cumulative average time per unit falls to a fixed share of its previous value, called the learning rate.
How do you calculate a learning curve?
With Wright's model, the cumulative average time for the first n units is a × n^b, where a is the first unit's time and b = log(learning rate) ÷ log 2. The total time is a × n^(b + 1), and the time of unit n alone is the total for n minus the total for n − 1.
What does an 85% learning curve mean?
Each doubling of cumulative output cuts the cumulative average time to 85% of its previous value, a 15% fall per doubling. If the first unit takes 120 minutes, the first 2 average 102, the first 4 average 86.7 and the first 8 average 73.7.
What is the difference between Wright's and Crawford's models?
Wright applies the learning rate to the cumulative average time; Crawford applies it to each unit's own time. With the same rate and the same first unit, Crawford predicts longer times. This calculator uses Wright's model.
What learning rate should I use?
The best source is your own history: fit the curve to unit times from an earlier, similar product. Without that, rates between 75% and 90% are often quoted for manual assembly, and rates closer to 100% for work paced by machines.
How do I find when a ramp-up will reach takt?
Enter the takt time or the standard time as the target. The calculator finds the first unit whose own time is at or below it, using the same learning rate.
Is anything I enter saved?
No. The calculator runs in your browser and nothing you type is sent to AutoOps AI or stored. There is no login.